New contractor being sought for N2 upgrade

Issued by SANRAL
Pietermaritzburg, Apr 24, 2018

The safety of road users is paramount and will not be compromised through the use of sub-standard material or poor performing service providers.

Thus, says the South African National Roads Agency SOC (SANRAL), the realignment of the N2 at the Umhlali and Umvoti River Bridges has been delayed because the contractor had failed to source materials as specified in the contract.

The final decision to terminate the contract was as a result of the contractor filing for business rescue, which ended up in the firm being sequestrated.

For several months, angry motorists have vented their frustration in the media at the delay in the completion of the upgrading of the N2 at the northern ends of the Umhlali and Umvoti River Bridges, where sharp curves were to be flattened to reduce the number of crashes.

Ridhwaan Mahomed, SANRAL Eastern Region project manager, said the agency's primary purpose is to provide a safe and efficient national road network for the benefit of all the people.

"In order for us to ensure that a reliable and resilient road has been constructed, quality control is of utmost importance.

"SANRAL has to ensure that all construction activities are in compliance with the specifications as set out in the contract to ensure that construction is undertaken to the highest standards.

"The contract documents also specify, among others, the minimum test results required to be achieved from various quality tests undertaken by an accredited laboratory."

Mahomed said the constructed pavement layer using the material from local material suppliers being used on the N2 project did not meet the required specifications.

"There are three probable reasons why the pavement layer failed. Firstly, the supplier may have supplied incorrect material; secondly, the contractor could have contaminated the material while processing and placing it on site; and thirdly, the material could have broken down during compaction of the layer."

He said SANRAL attempted to assist the contractor with a revised pavement design so as to limit the contractor's additional costs for removing and replacing the material.

However, SANRAL was made aware towards the latter part of 2017 that the contractor was placed under business rescue.

The original appointment value of the contract was R57.4 million. SANRAL only pays service providers for acceptable completed work. The contractor had only completed 27% of the original contracted work and was only paid for that amount of work.

Mahomed said when the contractor subsequently faced liquidation, a termination letter was sent.

"We are currently busy with a new tender process. The feedback received from the National Treasury is that we have to re-tender and cannot appoint the tenderer with the second highest points, which was SANRAL's initial recommendation as an attempt to expedite the process.

"We have to re-tender the entire contract and hopefully we will have a new contractor on site by September.

"Meanwhile, we humbly request all motorists to bear with us as we are trying our utmost best to resolve the situation," he said.